Question: 1 / 400

What is considered the primary product of a Risk Based Inspection (RBI) effort?

An inspection plan for each equipment item evaluated

The primary product of a Risk Based Inspection (RBI) effort is indeed an inspection plan for each equipment item evaluated. This inspection plan serves as a critical tool that outlines the specific inspections necessary based on the risk assessment of each piece of equipment. In an RBI framework, the process begins with identifying potential threats to safety and integrity while evaluating the historical performance, operating conditions, and other relevant factors.

The end goal is to create a tailored inspection strategy that prioritizes resources and focuses on areas with the highest risk, ensuring that inspection activities are both effective and efficient. By developing a detailed inspection plan, organizations can schedule inspections intelligently, manage risks proactively, and ultimately enhance the reliability and safety of their operations.

While other options, such as a detailed risk report or a compliance certificate, play important roles in the overall management of equipment risk, they are secondary outputs that support the development and refinement of the inspection plan rather than being the primary focus of an RBI effort. Similarly, a timeline for future inspections is a derivative of the inspection plan, indicating when the inspections will occur based on the prioritization.

Get further explanation with Examzify DeepDiveBeta

A detailed report of detected risks

A compliance certificate for the equipment

A timeline for future inspections